Prologis asked San Jose for a special-use permit to knock down five industrial buildings at 326 Charcot Avenue and put a three-story, 514,000-square-foot data center in their place, plus 30,000 square feet of office. The file is SP26-026, dated September 10. Design power is 99 megawatts, with an on-site substation and a generator yard. If the city and the state Public Utilities Commission both sign off, construction could start in the first quarter of 2028, run about 22 months, and put the plant online around 2030. Nothing is entitled yet.
The grid piece sits at PG&E’s Trimble substation on Component Drive, between North First Street and Orchard Parkway. Prologis would pay for the switchgear expansion and two transmission lines into the site, including a second independent route so the yard does not lean as hard on diesel. The company said it intends to enroll in San Jose Clean Energy’s Total Clean Energy product, or an equivalent, aiming at 100 percent carbon-free supply. PG&E’s statewide data-center queue hit 12.71 gigawatts at the end of June, more than double the March figure. In February the city said the utility was lining up hookups for a dozen unnamed large San Jose projects by 2030.
North San Jose already holds Google, Cisco, and Apple campuses and a growing stack of compute buildings. City tax math on a finished data center has been quoted in the $3 million to $7 million a year range for utilities and property. Water and ratepayer bill fights have stopped similar projects in other Bay Area towns. San Jose has so far treated the use as industrial reuse on land that was never going to become townhouses. A public hearing is required. The PUC still has to bless the Trimble work.
City data-center list: https://www.sanjoseca.gov/your-government/departments-offices/planning-building-code-enforcement/planning-division/data-center-and-other-large-energy-use-projects
Source: The Mercury News